Excalon Ltd was appointed by NGED to manage and install approximately 7.4km of 132kV double circuit ducting & cable infrastructure from Bustleholme to Kingstanding substations in the centre of Birmingham.
The Gorgie – Telford Road 132kV cable replacement project comprised of the installation of a twin 132kV ducting system for approx. 6km through the city of Edinburgh. The existing 132kV...
Excalon recently carried out 400kV high-voltage cable installation works for Envolve Infrastructure at Melksham 400kV Substation in support of National Grid’s upgrade of the site. The works formed part of...
Excalon recently carried out 400kV high-voltage cable installation works as part of the East Coast Upgrade Project on behalf of Scottish Power. The works formed part of a wider ECU2...
The Project scope included the installation of a triple 132kV circuit between Bradford West GSP Substation and Bradford SP substation with the exception of one of the circuits which connected...
Excalon have recently completed the installation of a quadruple 132kV circuit between a newly built GIS for Lostock Sustainable Energy Plant to two newly built Towers & an existing SPEN...
Excalon have been successful in securing a contract for the upgrading of the existing Coalburn – Middlemuir 132kV circuit. The existing circuit was required to be modified to facilitate the...
Excalon have been successful in securing a contract for the diversion of an existing twin 132kV circuit between Nechells and Sparkbroo k/Cheapside substations. The circuits are being diverted due to...
Excalon Ltd has been appointed Principal Contractor to manage, install and commission, 11 no. 132kV cable circuits, (8 ENWL and 3 National Grid) associated with construction of a new GIS...
Excalon was appointed by Iberdrola Engineering and Construction to manage and install new 132kV 10 way ducted system for cable tails within Maentwrog hydro-electric power station.
Excalon Ltd was appointed by Iberdrola Engineering and Construction to manage and install approximately 6km of 132kV double circuit ducting infrastructure from the existing Nuclear Power Station Site at Wylfa...
Hull Energy Works will be the first facility of its kind in the UK, using a combination of innovative renewable energy technologies to achieve a highly efficient mix of recycling...
The Project was to install and lay a triple 132kV circuit between Bradford West GSP Substation and Bradford SP substation with the exception of one of the circuits which connected...
Between 2008 and 2014, Excalon diverted and relocated all the EHV, HV, LV and service electricity cables, substations and associated equipment necessary for the construction of the new branch lines.
Commencing in 2013, Excalon has been diverting and relocating all EHV/HV/LV and service electricity cables, substations and associated equipment together with installing innovative ‘multi-utility’ ductings in the ground and providing...
Multi-utility ducting was installed in trenches in the vicinity of Corporation Street directly outside The Co-operative bank. The photos show the actual duct formation in trenches for multi-utilities and the...
The project at Harcourts Liverpool was for two specialist road crossings as part of a larger District heating project. The Great Howard Street crossing was pipejacked at 5.5m deep underneath...
The project is on the back of the District Heating Works in Manchester City Centre and is for the installation of approximately 2,500m of 11kV cable through installed ducts and...
The Project was to install and lay a twin 132kV circuit between Bustleholm Substation and Perry Barr Substation over a distance of 6km. The works where required due to the...
Phase 1 of the project was to temporarily divert a 132kV oil circuit crossing a Network Rail bridge, allowing the bridge to be demolished and rebuilt offering a higher clearance...
If you would like a member of our team to give you a call, just enter you name and telephone number and we will call you as soon as we can.