The Project scope included the installation of a triple 132kV circuit between Bradford West GSP Substation and Bradford SP substation with the exception of one of the circuits which connected to tower PLK/05 close the Bradford SP Substation. The full route covered a distance of 10.1km.

The initial phase of the Works required site investigation Works to enable the design verification of the outline client design. Trial holes were undertaken at proposed joint bay locations and at areas of specific engineering difficulties.

The route had various challenges including works to cross a major culvert which required a specialised design to cross whilst protecting the 132kV cables, a Network Rail Bridge which required another specialised design provided by Northern Powergrid to install cable trays underneath the road deck whilst keeping a safe distance from the Overhead Lines for the railway. Significant inhouse traffic management was required along the full route which runs through the city centre of Bradford, especially on Canal Road which is one of the main roads within Bradford and crossing major traffic sensitive junctions.

The complexity of the route required a full time customer liaison officer who constantly communicated with a number of Stakeholders, including the Local Council, Network Rail for the bridge crossing, Yorkshire Water, Northern Gas Networks for crossing their assets, Several local schools two local parish councils, and all residents in the area affected by the work.

The duct installation was completed utilising Excalon’s in house excavation teams supported with specialists to undertake elements of the Works. Each of the circuits were installed by one of Excalon’s specialist EHV cable teams through ducts, using our cable trailer and installation equipment.

Excalon’s Jointers and engineers completed the 132kV jointing works and HVAC testing to commission the circuits, working under the technical specification procedures of NPg. This included working with other utility asset owners to enable jointing works in close proximity to their assets.

Specilised Design under the Queens Road Network Rail Bridge meant close working with Network Rail to enable the works under the bridge. The design called for working with other subcontractors within a very small window of opportunity on track possessions to install GRP tray work under the road deck before installing the ducting for the triple 132kV circuit.

Bespoke Civil works design for the Ling Bob Culvert. During trial hole investigations it was found that the culvert that ran near the Ling Bob Pub was extremely large and the bottom of it was over 2m underneath the road deck.
With consultations with our Designers, an option was found to take the roof off the culvert and replace it with bespoke pre cast concrete slabs which had ducting already cast inside. This protected the cables while going shallower than normal for 132kV cables.

Download Case Study – 132kV Bradford West

 

Case Study Specifics

Client: Northern Powergrid

Duration: 30 Months

Services Provided:

  • Principle Contractor
  • Full Project Management
  • Civil Design Verification
  • Stakeholder Management
  • Site Management & Supervision
  • Traffic Management
  • Excavation and Civil works
  • 132kV Jointing
  • HV AC Testing
  • Fibre cable installation
  • Fibre Jointing
  • De-oiling Works of the existing circuits