Case Study

Case Studies Home > East Coast Upgrade 400kV

East Coast Upgrade 400kV

Excalon recently carried out 400kV high-voltage cable installation works as part of the East Coast Upgrade Project on behalf of Scottish Power. The works formed part of a wider ECU2 project to increase transfer capacity traversing the B4 boundary between SPT & SHETL.

In addition to a 400m span of ducting and cable installation, the project consisted of the creation of foundations for new sealing end structures, along with the installation of those structures.

Scope of Works

The project involved the following specification & technical requirements:

– 400kV cable (incl. earthing and fibre optic) handling, installation in the presence of cable manufacturer representative.
– Termination and testing of the FO cables.
– Cable duct supply & installation
– Civil works associated with the cable sealing end foundations based on cable manufacturer’s foundation design

Special Engineering Difficulties (SED’s)

A number of SEDs were identified along the cable route, bespoke solutions to these were provided by Excalon working closely with the client and relevant stakeholders. SEDs encountered on this project required installation of ducting under a number of sections of existing fences, stone retaining walls, & sections of existing roads/tracks.

Foundation Construction

The project involved a range of civil works associated with the cable sealing end foundations based on cable manufacturer’s foundation design. Setting out of the construction corridor was provided by Excalon, in addition to installation of marker posts. Once complete Excalon installed the support structures to facilitate final connections, testing & commissioning.

Conclusion

This project demonstrated Excalon’s ability to safely and efficiently deliver high-voltage cable installation services within a technically complex environment. Our team worked closely with the client, relevant stakeholders and specialist subcontractors to complete the installation in line with technical requirements and under strict safety protocols.

The successful execution of this work supported the wider ECU2 project increasing the transfer capability of the circuits traversing the B4 boundary between SPT and Scottish Hydro Electric Transmission Ltd (SHETL).

Download Case Study – East Coast Upgrade 400kV

Case Study Specifics

Client: SPEN

Duration: 16 Months

Services Provided:

  • Project Management
  • Site Management
  • Civil Design Verification
  • Excavation and Civil works
  • Ducting & Cable Installation
  • Lifting cables up CSE
  • Trench Excavation
  • Construction of Foundations
  • Installation of Support Structures