Case Studies Home > Manchester HV Cable Network
The project is on the back of the District Heating Works in Manchester City Centre and is for the installation of approximately 2,500m of 11kV cable through installed ducts and on ladder racking on the scheme route.
The project required Excalon to install sections of ladder racking within buildings and car parks to enable Excalons in house team to install the 11kV cable.
Excalons resources have installed cable within the buildings to the RMU locations. Excalon in-conjunction with Atlas Utilities Ltd cleated the cable to the ladder racking, completed intermediate joints and the associated terminations.
Senior authorised personnel along with site management have been provided for the project.
The civils teams from Excalon have completed the joint bays for the Works and have co-ordinated the works alongside the requirements of third party stakeholder.
Excalons resources have engaged with the stakeholders on the installation of RMU units into the buildings and are co-ordinating the installations to meet the end users expectations and minimise disruption.
Client: Vital Energy
Duration: 14 Months
Services Provided:
If you would like a member of our team to give you a call, just enter you name and telephone number and we will call you as soon as we can.