Case Studies Home > "Multi-Utility" works for the Second City Crossing (2CC) through Manchester
Since 2008, Excalon has worked closely with TfGM, MPT, Manchester City Council, ENWL and other utility companies in diverting and relocating existing utilities equipment to provide a swept path for new lines and stops, as follows:
Section 1 – Corporation Street/Todd Street Multi-utility ducting was installed in trenches in the vicinity of Corporation Street directly outside The Co-operative bank. The photos show the actual duct formation in trenches for multi-utilities and the “As-built” and “Cross section” technical drawings. The installation was in an area of archaeological interest and was subject to constant monitoring by an appointed archaeologist who was in attendance whilst work was being undertaken.
Section 2 – Corporation Street/Selfridges department store
Multi-utility ducting was installed in trenches in this area. The photos show the actual duct formation in trenches for multi-utilities and the “As-built” and “Cross section” technical drawings. Special engineering obstacles encountered included purpose built troughs placed during previous infrastructure/building restoration works. It was necessary to undermine and under pin the troughs.
Section 3 – Corporation Street/Market Street
Multi-utility ductings were installed in the vicinity of this junction which is in one of the busiest shopping districts in Manchester. The photos show the actual duct formation in trenches for multi-utilities and the “As-built” and “Cross section” technical drawings. Working in such a busy thoroughfare, it was necessary that measures were taken to ensure local businesses remained unaffected and pedestrians could pass through whilst work was undertaken. The innovative solution to the challenge was to place a purpose built temporary vehicle access bridge over the excavations. A number of other smaller purpose built footbridges were also used to ensure the public had convenient access to businesses and shops, etc. During excavation, old structures were uncovered and were deemed to be of archaeological interest and it was necessary that the work was then subject to constant monitoring by the appointed archaeologist.
Section 4 – Cross Street/Chapel Walks/Cheapside/King Street
Multi-utility ductings were installed in this conservation area, designated to be of heritage and archaeological interest. The photos show the actual duct formation in trenches for multi-utilities and the “As-built” and “Cross section” technical drawings. Working in close proximity to local businesses, shops and resturants, it was necessary to provide purpose built footbridges to enable public access and minimise disruption to businesses. The diversions also entered the narrow side streets and alleyways, which had to be cleared and designated areas established for the storage of waste bins, etc. Elements of the work had to be undertaken at night to accommodate the needs of businesses. During the planning stage it was acknowledged that this work would disturb the known heritage and archaeological area (i.e, old structures and covered graveyards) and would therefore be subjected to rigorous monitoring by heritage and archaeological personnel. It was also necessary to work closely with the archaeologist and the Church authorities along Cross Street where it was necessary for others to exhume around 120 bodies in the former graveyard which dated back to 1694. Acoustic barriers were used to reduce the sound of the excavators.
Section 5 – Albert Square
Multi-utility ductings were installed in this conservation area in close proximity to the Manchester Town Hall which is a Grade 1 listed Gothic Victorian building and Albert Square which is a public square with a number of significant monuments and statues. The photos show the actual duct formation in trenches for multi-utilities and the “As-built” and “Cross section” technical drawings. Works were planned to be executed in phases (with 24 hour working to achieve the critical path for successful completion) to minimise disruption to pre-planned civic functions and City Centre events including the popular Christmas Markets. Protective hoardings were set up in and around Albert Square to protect the trees, monuments and statues whilst the work was undertaken. All work was subject to rigorous monitoring by heritage and archaeological personnel.
Section 6 – Princess Street/St Peters Square
Multi-utility ductings were installed in this conservation area in close proximity to the Manchester Town Hall and the coroners count. The photos show the actual duct formation in trenches for multi-utilities and the “As-built” and “Cross section” technical drawings. Works were planned to be executed in agreed shift patterns to minimise disruption to all. All work was subject to rigorous monitoring by heritage and archaeological personnel.
Section 7 – St Peters Square/Oxford Street
Multi-utility ductings are being installed in this area in the vicinity of Manchester Central Library, The Midland Hotel and the recently repositioned cenotaph. The photos show the actual duct formation in trenches for multi-utilities and the “As-built” and “Cross section” technical drawings. Works are being undertaken in agreed shift patterns to minimise disruption to all. All work is subject to rigorous monitoring by heritage and archaeological personnel.
Client: TfGM/MPT/ENWL/MCC/BT
Duration: 6 years
Services Provided:
If you would like a member of our team to give you a call, just enter you name and telephone number and we will call you as soon as we can.